Aquatic Center Taking Shape for 2019 Opening

 
The highly anticipated Aquatic Center in Plymouth is on track to be finished August 2019, just in time for the start of Plymouth Community School Corporation’s 2019-2020 school year. Construction is roughly 25% finished with three walls already up, and the south wall being built. Concrete work is continuing with some of the bleachers in place. Steel truss for the roof are also being installed. The completed building will be 27,000 sq. ft. with 10 lanes, 2 diving boards, and seating for over 435 people. The Aquatic Center will enhance quality of life for all residents and serve as the cornerstone for recreational amenities in the community. The facility is a $8.4 million capital investment developed through partnerships with over 17 agencies and organizations.